Chocs Away at Barry Callebaut

 Breaking News
  • Heineken Delivers Strong Top-line Growth in 2019 Global brewer Heineken achieved 5.6% organic growth in net revenue (beia) to €23.894 billion for 2019 and operating profit grew 3.9% organically to €4.020 billion. However, the operating profit margin...
  • Molson Coors Partners With e.fundamentals to Help Drive UK Online Sales Molson Coors, one of the world’s largest brewers, has partnered with ecommerce analytics provider e.fundamentals to help drive sales of its beers through retailers’ websites in the UK. E.fundamentals’ service...
  • Manor Farm Wins IFSA Best Sustainable Food Product Award 2020 Irish chicken producer Manor Farm has won the IFSA (Irish Foodservice Suppliers Alliance) Best Sustainable Food Product Award 2020. Manor Farm, received the award for the company’s ‘Farmers to Market’...
  • Heineken Announces CEO Succession Jean-François van Boxmeer (pictured left), Chairman and CEO of Heineken, is to step down following his successful 15 year leadership of the company. He will be succeeded by Dolf van...
  • DMK Group Aims to Optimise Ice Cream Production DMK Group, Germany’s largest dairy co-operative, intends to streamline the production network in its ice cream business unit. This involves selling its Waldfeucht-Haaren production site in North Rhine-Westphalia. Schwarz Produktion,...

Chocs Away at Barry Callebaut

Chocs Away at Barry Callebaut
September 09
11:48 2014

Barry Callebaut, the world’s largest manufacturer of cocoa and chocolate products, recognised that a significant increase in operational efficiencies could be achieved through the installation of a robotic palletising system at its Banbury plant in England.

The company had recently initiated a major investment programme, in line with its ‘cost leadership’ strategy pillar, across all areas of its manufacturing process to deliver an increase in capacity and optimise production flow. To further improve efficiencies, a three phase investment over two years was now planned for the palletising area with the implementation of a fully integrated robotic solution to an existing line.

The new system was required to provide greater flexibility and reliability, utilise limited floor area, simplify operational procedures and reduce maintenance costs. In addition, it would have to overcome the challenges of picking up multiple sizes of boxes (between 10kg and 25kg), increased cycle rates and be fully compliant with the company’s stringent health and safety disciplines.

Barry Callebaut commissioned CKF Systems of Gloucester as its project partner to design, build and install an integrated robotic palletising system within its manufacturing plant.

“We were impressed by work CKF had recently undertaken for a major confectionary brand,” explains Barnz Parkin, Project Management Engineer, Barry Callebaut. “We spoke to the project manager, who has a wealth of experience and we regard highly and he provided a sound endorsement; a good partner, talented, flexible and reliable. We looked at nine different organisations, only CKF demonstrated a complete understanding of our situation and submitted a working solution that would improve our capabilities in line with budget and expectations. It was a major undertaking for the business and therefore essential that we made the right decision.”

The initial project is designed around a single robot cell but with the ability to palletise three different SKU’s at the same time. The cell, incorporating an ABB IRB 660 with a bespoke gripper, has been designed by CKF. It utilises 3D Inventor and Robot Studio simulation to ensure the full range of case sizes, weights and configurations can be handled and are able to pick layer sheets. The case feed system comprises a high level interface complete with divert station and bar code detection, to direct the flow of designated cases to the robot cell and separate in to three defined collation stations. Each station incorporates an identical conditioning section to orientate and collate the cases into defined rows and counts for the robot pick to create the pallet pattern. A dedicated pallet load station is positioned at the end of each collation station and the cell also includes two separate layer sheet feed sections to handle both Chep and Euro pallet sized sheets.

The overall system includes two dedicated pallet denesters, i.e. Chep and Euro, loaded pallet discharge station and twin shuttle car. The shuttle car arrangement is designed to receive individual pallets, on demand, from the designated denester and deliver to the relevant pallet load station at start of production. The shuttle is also designed to receive and exchange both loaded and empty pallets, with the loaded pallets delivered to the unload station before the car returns to the denester stations to collect the next pallet. The final configuration of the system includes provision for the introduction of a second robot cell and a fully automatic spiral wrapping machine.

The complete operation is fully contained within a guard enclosure incorporating strategically positioned light beams, roller shutter door and interlocks to meet the very highest safety standards with zoned safety areas to maximise overall system efficiency.


Warning: count(): Parameter must be an array or an object that implements Countable in /home/fdbusiness/public_html/wp-content/themes/legatus-theme/includes/single/post-tags.php on line 5
Share

About Author

mike

mike

Related Articles

Food & Drink Business Conference & Exhibition 2016

Upcoming Events

[eventlist]

Jobs: Logistics

find food jobs

The Magazine

F&D Business Preferred Suppliers

New Subscriber

Subscribe Here



Advertisements